New production plant is on the threshold of start-up

New production plant is on the threshold of start-up

General construction contractor LLC PSK Shchekinoazot and its subcontractor SC Construction Holding Management Company (Ekaterinburg) keep constructing the plant. Earthworks and foundations are accomplished, construction of production and auxiliary building is completed and finishing works are coming to an end. Steelstructures and equipment are installed and being anticorrosive treated, process pipework is being over.

Electric equipment and instrumentation cables, automated process control system are in the course of installation.

The equipment primary examination is in progress, pipes are being hydrotested. DME production site is under improvements.